Newsletter Update 18A
Garage Repair progress report
NON STOP WORK SCHEDULE for the next TWO WEEKS
PAVING, SIDEWALK AND STONEWORK:
- Friday 27th November - Prepare deck for Asphalt (Paving)
- Saturday 28th November - Form the sidewalk
- Sunday 29th November - Start backfilling the deck
- Monday 30th November - Pour concrete for sidewalk
- Tuesday 01st December - Start Paving
- Friday 04th December - Inspection
- Saturday 05th December - Stone Interlocking
- Sunday 06th December - Stone Interlocking
- Monday 07th - Friday 11th December - Complete all paving and sidewalk
Crews will be working non-stop 7 days a week in order to finish the project. They are expected to work late into the evening and flood lights will be provided if needed.
RESTRICTED ACCESS:
Access to the Visitor Parking and Parking behind the building will be restricted at times. Residents parking at the back will be able to park in Visitors' parking without a permit during the paving.
Updates will be posted as progress is made.
Place Royale Board of Directors thanks all residents for their continued support in improving our property. Thank you.