Thursday, November 26, 2015

Newsletter Update 18A

Newsletter Update 18A


Garage Repair progress report

NON STOP WORK SCHEDULE for the next TWO WEEKS

PAVING, SIDEWALK AND STONEWORK:

- Friday 27th November - Prepare deck for Asphalt (Paving)
- Saturday 28th November - Form the sidewalk
- Sunday 29th November - Start backfilling the deck
- Monday 30th November - Pour concrete for sidewalk
- Tuesday 01st December - Start Paving 
- Friday 04th December - Inspection
- Saturday 05th December - Stone Interlocking
- Sunday 06th December - Stone Interlocking
- Monday 07th - Friday 11th December - Complete all paving and sidewalk

Crews will be working non-stop 7 days a week in order to finish the project. They are expected to work late into the evening and flood lights will be provided if needed.
 

RESTRICTED ACCESS:

Access to the Visitor Parking and Parking behind the building will be restricted at times. Residents parking at the back will be able to park in Visitors' parking without a permit during the paving.

Updates will be posted as progress is made.  

Place Royale Board of Directors thanks all residents for their continued support in improving our property. Thank you.