Friday, November 06, 2015

Newsletter Update 18

Newsletter Update 18


Garage Repair progress report
 

WATERPROOFING THE DECK (Membrane):

The Structural Engineers CION has examined the deck and approved the installation of the waterproofing.
 

WATERPROOFING SCHEDULE:

- Saturday 07th October - Grind the deck
- Sunday 08th October - Grind the deck and prepare for waterproofing
- Monday 09th October - Inspection and installation of waterproofing
- Tuesday 10th - Thursday 12th October - Installation of waterproofing
- Friday 13th October - Inspection
- Sunday 15th October - Completion of membrane and final inspection (weather permitting)

The Waterproofing Crew will be working for 10 days non-stop in order to finish the project. They are expected to work late into the evening and flood lights will be provided if needed.

RESTRICTED ACCESS:

Access to the Visitor Parking and Parking behind the building will be restricted in order to complete the waterproofing. Residents parking at the back will be able to park in Visitors' Parking without a permit during the waterproofing.

Updates will be posted as information becomes available.  

Place Royale Board of Directors thanks all residents for their continued support in improving our property. Thank you.