Wednesday, December 09, 2015

Newsletter Update 18B

Newsletter Update 18B


Garage Repair progress report

- Waterproofing - completed
- Construction of Sidewalk from Visitor Parking to front Entrance - completed
- Construction of Sidewalk East Side to main entrance - completed
- Catch Basins in Visitor Parking (Four) - dug out and repaired
- First layer of asphalt - applied

- Second layer of asphalt will be laid in May 2016
- Ongoing - Construction of the Circle at the front of the building will continue (Dependant on Weather)
- Stone Interlocking work will continue until completed (Dependant on Weather)

Crews will continue to work late into the evening, 7 days a week, in order to finish the project.

Updates will be posted as progress is made.  

Place Royale Board of Directors thanks all residents for their continued support in improving our property. Thank you.