Newsletter Update 18B
Garage Repair progress report
- Waterproofing - completed
- Construction of Sidewalk from Visitor Parking to front Entrance - completed
- Construction of Sidewalk East Side to main entrance - completed
- Catch Basins in Visitor Parking (Four) - dug out and repaired
- First layer of asphalt - applied
- Second layer of asphalt will be laid in May 2016
- Ongoing - Construction of the Circle at the front of the building will continue (Dependant on Weather)
- Stone Interlocking work will continue until completed (Dependant on Weather)
Crews will continue to work late into the evening, 7 days a week, in order to finish the project.
Updates will be posted as progress is made.
Place Royale Board of Directors thanks all residents for their continued support in improving our property. Thank you.
Wednesday, December 09, 2015
Thursday, November 26, 2015
Newsletter Update 18A
Newsletter Update 18A
Garage Repair progress report
NON STOP WORK SCHEDULE for the next TWO WEEKS
PAVING, SIDEWALK AND STONEWORK:
- Friday 27th November - Prepare deck for Asphalt (Paving)
- Saturday 28th November - Form the sidewalk
- Sunday 29th November - Start backfilling the deck
- Monday 30th November - Pour concrete for sidewalk
- Tuesday 01st December - Start Paving
- Friday 04th December - Inspection
- Saturday 05th December - Stone Interlocking
- Sunday 06th December - Stone Interlocking
- Monday 07th - Friday 11th December - Complete all paving and sidewalk
Crews will be working non-stop 7 days a week in order to finish the project. They are expected to work late into the evening and flood lights will be provided if needed.
RESTRICTED ACCESS:
Access to the Visitor Parking and Parking behind the building will be restricted at times. Residents parking at the back will be able to park in Visitors' parking without a permit during the paving.
Updates will be posted as progress is made.
Place Royale Board of Directors thanks all residents for their continued support in improving our property. Thank you.
Garage Repair progress report
NON STOP WORK SCHEDULE for the next TWO WEEKS
PAVING, SIDEWALK AND STONEWORK:
- Friday 27th November - Prepare deck for Asphalt (Paving)
- Saturday 28th November - Form the sidewalk
- Sunday 29th November - Start backfilling the deck
- Monday 30th November - Pour concrete for sidewalk
- Tuesday 01st December - Start Paving
- Friday 04th December - Inspection
- Saturday 05th December - Stone Interlocking
- Sunday 06th December - Stone Interlocking
- Monday 07th - Friday 11th December - Complete all paving and sidewalk
Crews will be working non-stop 7 days a week in order to finish the project. They are expected to work late into the evening and flood lights will be provided if needed.
RESTRICTED ACCESS:
Access to the Visitor Parking and Parking behind the building will be restricted at times. Residents parking at the back will be able to park in Visitors' parking without a permit during the paving.
Updates will be posted as progress is made.
Place Royale Board of Directors thanks all residents for their continued support in improving our property. Thank you.