Newsletter Update 18A
Garage Repair progress report
NON STOP WORK SCHEDULE for the next TWO WEEKS
PAVING, SIDEWALK AND STONEWORK:
- Friday 27th November - Prepare deck for Asphalt (Paving)
- Saturday 28th November - Form the sidewalk
- Sunday 29th November - Start backfilling the deck
- Monday 30th November - Pour concrete for sidewalk
- Tuesday 01st December - Start Paving
- Friday 04th December - Inspection
- Saturday 05th December - Stone Interlocking
- Sunday 06th December - Stone Interlocking
- Monday 07th - Friday 11th December - Complete all paving and sidewalk
Crews will be working non-stop 7 days a week in order to finish the project. They are expected to work late into the evening and flood lights will be provided if needed.
RESTRICTED ACCESS:
Access to the Visitor Parking and Parking behind the building will be restricted at times. Residents parking at the back will be able to park in Visitors' parking without a permit during the paving.
Updates will be posted as progress is made.
Place Royale Board of Directors thanks all residents for their continued support in improving our property. Thank you.
Thursday, November 26, 2015
Friday, November 06, 2015
Newsletter Update 18
Newsletter Update 18
Garage Repair progress report
WATERPROOFING THE DECK (Membrane):
The Structural Engineers CION has examined the deck and approved the installation of the waterproofing.
WATERPROOFING SCHEDULE:
- Saturday 07th October - Grind the deck
- Sunday 08th October - Grind the deck and prepare for waterproofing
- Monday 09th October - Inspection and installation of waterproofing
- Tuesday 10th - Thursday 12th October - Installation of waterproofing
- Friday 13th October - Inspection
- Sunday 15th October - Completion of membrane and final inspection (weather permitting)
The Waterproofing Crew will be working for 10 days non-stop in order to finish the project. They are expected to work late into the evening and flood lights will be provided if needed.
RESTRICTED ACCESS:
Access to the Visitor Parking and Parking behind the building will be restricted in order to complete the waterproofing. Residents parking at the back will be able to park in Visitors' Parking without a permit during the waterproofing.
Updates will be posted as information becomes available.
Place Royale Board of Directors thanks all residents for their continued support in improving our property. Thank you.
Garage Repair progress report
WATERPROOFING THE DECK (Membrane):
The Structural Engineers CION has examined the deck and approved the installation of the waterproofing.
WATERPROOFING SCHEDULE:
- Saturday 07th October - Grind the deck
- Sunday 08th October - Grind the deck and prepare for waterproofing
- Monday 09th October - Inspection and installation of waterproofing
- Tuesday 10th - Thursday 12th October - Installation of waterproofing
- Friday 13th October - Inspection
- Sunday 15th October - Completion of membrane and final inspection (weather permitting)
The Waterproofing Crew will be working for 10 days non-stop in order to finish the project. They are expected to work late into the evening and flood lights will be provided if needed.
RESTRICTED ACCESS:
Access to the Visitor Parking and Parking behind the building will be restricted in order to complete the waterproofing. Residents parking at the back will be able to park in Visitors' Parking without a permit during the waterproofing.
Updates will be posted as information becomes available.
Place Royale Board of Directors thanks all residents for their continued support in improving our property. Thank you.