Wednesday, September 15, 2021

Newsletter Update 36

 Newsletter Update 36


Construction

Construction work on the West Side B1 and B2 Exits will start at the end of September 2021. Soffit work will be completed. This may require residents to park their vehicles in the Visitors parking until the work is completed.

Window Cleaning

Anchor testing has been completed and Window Cleaning is now scheduled for September 27th 2021. Please remove your screens so that the window cleaners have access.

Fire Protection

Proline Annual Fire Inspection: Suites with deficiencies will be contacted and action in repairing the deficiency is Mandatory under the Fire Code. Access to Suites will be required. Should you not be at home, Security and Management will be accompanying the Contractor to your suite and will leave a note letting you know that they have accessed your suite and the work was completed.

Carpet Cleaning

Carpets will be steam cleaned in early October.

Ensure that your garbage bags are fully pushed into the chute and that they have gone down. Please do not leave garbage on the floor by the garbage chute.

Place Royale Board of Directors
Dev, Val, Danielle, Manny, Mohammed