Please be advised that Fan Coil maintenance in units will be starting June 26th, 2014.
We expect to finish three floors per day. Schedule as follows:

Thursday June 26th:  Pent House - 19th Floor
Friday June 27th:  18th Floor -16th Floor
Monday June 30th:  15th Floor - 12th Floor
Wednesday July 2nd:  11th Floor - 9th Floor 
Thursday July 3rd:  8th Floor - 6th Floor
Friday July 4th:  5th Floor - 3rd Floor
Monday July 7th:  2nd Floor - Ground Floor

Starting 9AM each day till 5PM


Access to your unit is necessary to complete this work. If the Fan Coil cleaning team cannot get access to your unit for some reason they will move on to the next unit. Cleaning the Fan Coil in a unit takes about half an hour. Management would not be able to give an approximate time of entry to your suite.

Please make arrangements to have someone home. If you cannot be at home, Management Staff or a Concierge will go with technicians to complete the work in your unit. Otherwise, a second visit will be scheduled and the costs will be charged back to your suite account.

NOTE: There should be access to reach the Fan Coil unit. Residents are to remove any valuable articles and furnishings that may be damaged because of their proximity to the Fan Coil unit.

Your cooperation is very much appreciated.